NARRATIVE REPORT FOR ZMB/26/031
ST. MARY’S MISSION HOSPITAL LAUNDRY CONSTRUCTION - UPDATE ON PROGRESS
NARRATIVE REPORT FOR ZMB/26/031
PROJECT NAME: ST. MARY’S MISSION HOSPITAL LAUNDRY CONSTRUCTION
DATE: 22TH SEPTEMBER, 2026
PREPARED BY: SR. DOREEN MALUBA; SFMA
MONTH/YEAR: SEPTEMBER, 2026
BENEFACTOR: ROME 1% DEVELOPMENT FUND
INTRONDUCTION
Greetings from St. Mary’s Mission Hospital. The Laundry construction started on 20th June 2026. On behalf of St. Mary’s Mission Hospital, we sincerely thank you. I am glad to present to you an update of the works done so far. I would like to state that the project has delayed due to some challenge in terms of finances to fully complete the painting and the ceiling boards. We are at 80% completion and we are very grateful to you all.
Kindly find below a table that gives a description of the works done. We have also attached photos of the works as well as the income and expenditure statement for the period under review.
SUMMARY TABLE OF THE PROJECT
|
SCOPE OF THE PROJECT |
|
|
TARGETS |
|
|
COMPLETED TASKS |
ü Construction of the sub structure ü Construction of the supper structure almost complete. ü Roofing is done ü Plumbing works are at 80% completion ü Electrical works at 80%. Waiting for power to be installed. |
|
GOALS/TASKS PLANNED FOR NEXT PHASE |
|
|
CHALLENGES ENCOUNTERED |
|
|
INTERVENTIONS |
|
IMPORTANT NOTES.
- The washing machines were procured before completing the building for fear the funds can be swallowed in the construction since the funds were inadequate. We negotiated for the lowest bidder who was also recommended by the District Council within the District. Works are at 80% completion.
Photo's uploaded here: